Question 1
The "Net Present Value" (NPV) method assumes that intermediate cash flows are reinvested at:
View Explanation
A key assumption of NPV is that cash flows generated during the project life are reinvested at the firm's Cost of Capital (Required Rate of Return), which is considered more realistic than the IRR assumption.
Question 2
If the Net Present Value (NPV) of a project is ZERO, then the Internal Rate of Return (IRR) is:
View Explanation
IRR is defined as the discount rate at which NPV is zero. If NPV calculated at the cost of capital is zero, then the IRR must be exactly equal to that cost of capital.
Question 3
A major limitation of the "Payback Period" method is that it:
View Explanation
Payback period only focuses on how quickly the initial investment is recovered. It ignores profitability (total cash flows) and the Time Value of Money (unless discounted payback is used).
Question 4
The "Discounted Payback Period" will always be ______ than the simple "Payback Period" for the same project (assuming positive discount rate).
View Explanation
Because future cash flows are discounted (reduced in value), it takes more time (more years) to recover the initial investment in present value terms compared to nominal terms.
Question 5
A project is acceptable based on the "Profitability Index" (PI) method if:
View Explanation
PI = PV of Cash Inflows / Initial Investment. If PI > 1, it means the project generates more value than it costs (NPV is positive), so it should be accepted.
Question 6
"Sensitivity Analysis" in capital budgeting involves:
View Explanation
Sensitivity Analysis helps identify which variables (like sales price or raw material cost) the project is most sensitive to, indicating where the risk lies.
Question 7
When evaluating mutually exclusive projects, if NPV and IRR give conflicting rankings, which method should be preferred?
View Explanation
NPV is preferred because it measures the absolute addition to shareholder wealth and uses a realistic reinvestment rate (Cost of Capital), whereas IRR assumes reinvestment at the IRR itself, which may be unrealistic.
Question 8
The process of calculating the Present Value of future cash flows is known as:
View Explanation
Discounting is the reverse of compounding. It determines what a future amount is worth today, given a specific interest rate.
Question 9
The "Accounting Rate of Return" (ARR) method uses:
View Explanation
Unlike other methods (NPV, IRR, Payback) which use Cash Flows, ARR uses Accounting Profit from the P&L account.
Question 10
Which method allows ranking of projects with different investment outlays?
View Explanation
NPV gives an absolute value which favors larger projects. PI (Benefit-Cost Ratio) gives a relative measure (Value per rupee invested), making it better for ranking projects of different sizes.
Question 11
The "Modified Internal Rate of Return" (MIRR) addresses which major flaw of the standard IRR method?
View Explanation
Standard IRR assumes cash flows are reinvested at the IRR rate (often unrealistic). MIRR assumes reinvestment at the Cost of Capital (WACC), providing a more accurate picture of profitability.
Question 12
The "Risk-Adjusted Discount Rate" (RADR) method accounts for risk by:
View Explanation
Under RADR, a higher discount rate (Risk-Free Rate + Risk Premium) is used for riskier projects, which lowers the Present Value of future inflows, making the acceptance criteria stricter.
Question 13
In Capital Budgeting, "Real Options" refer to:
View Explanation
Traditional NPV ignores future flexibility. Real Options approach values the ability to change course (e.g., abandoning a failing project early), adding value to the investment.
Question 14
In the "Certainty Equivalent" (CE) method of risk analysis:
View Explanation
Instead of adjusting the rate (RADR), CE adjusts the numerator (Cash Flows) by multiplying uncertain flows with a CE coefficient (0 to 1) to get certain flows, then discounts them at the risk-free rate.
Question 15
In a "Replacement Decision" (replacing old machine with new), the relevant cash flows are:
View Explanation
Decision making focuses on "what changes". Only the extra cash inflow or cost saving generated by the new machine over the old one is relevant.
Question 16
A "Decision Tree Analysis" is most useful in capital budgeting when:
View Explanation
Decision trees map out sequential decisions and uncertain outcomes (with probabilities), allowing managers to evaluate complex, multi-stage investment proposals.
Question 17
A project may have "Multiple Internal Rates of Return" (Multiple IRRs) if:
View Explanation
When the direction of cash flows changes more than once (e.g., heavy maintenance cost in year 5 causing a net outflow), the IRR equation can have multiple mathematical solutions, making IRR unreliable.
Question 18
The situation where a firm has more acceptable projects (Positive NPV) than it has funds available to invest is called:
View Explanation
Under Capital Rationing, the firm must select the combination of projects that maximizes total NPV within the budget constraint (often using Profitability Index).
Question 19
When evaluating a new project, which of the following costs should be IGNORED (treated as irrelevant)?
View Explanation
Sunk costs are past costs that have already been incurred and cannot be recovered (e.g., money spent on market research last year). They should not affect the decision to accept/reject a project today.
Question 20
What is the purpose of "Post-Audit" in Capital Budgeting?
View Explanation
Post-Audit provides feedback, helps identify why forecasts went wrong, and improves future decision-making. It is a control mechanism.